November Progress Photos
Second floor structure steel installation
View of structural steel from inside
The auxiliary gym and dance studio CMU wall is ready for exterior weatherproofing and a brick facade
Wiring and breakers for the science lab
Plumbing rough-ins and ductwork boy's locker room
Electrical rough-ins and ductwork girl's locker room
Site access plan
English
Site access plan
Spanish
October Progress Photos
CMU Bearing Walls
Second Floor Steel Framing
Second Floor Decking
Stair 12
Site access plan
English
Site access plan
Spanish
September Progress Photos
Corridor 1
Steel connections and CMU walls
Concrete finishing
CMU installation
CMU installation
CMU installation
Aerial of bus loop, curb, gutter, sidewalk
Site access plan
English
Site access plan
Spanish
August Progress Photos
Critical Slab pour connecting the existing building with the new addition
New addition slab
Pivotal steel in place to connect the existing building with the new addition
Installation of new stormwater management system
Site Access Plan English
Site Access Plan Spanish
July Progress Photos
Street view of new stairwell
Interior view of new stairwell
Interior school corridor 1
Interior school corridor 1 ceilings
Corridor 1 ceiling work area is highlighted in orange
Closed Sigo Creek bus loop highlighted in orange
Site Access Plan English
Site Access Plan Spanish
June Progress Photos
Snip of blueprint and planning of all underground work
Stair 11 slab
Underground electrical lines
CMU Walls
Upcoming Work Locations:
Corridor 1 ceiling work area is highlighted in orange
Upcoming Work Locations:
Closed Sligo Creek bus loop highlighted in orange
Site Access Plan English
Site Access Plan Spanish
May Progress Photos
Underground plumbing & sanitary lines
Underground plumbing & Sanitary Lines
Site Access Plan
English
Site Access Plan
Spanish
April Progress Photos
Old foundation being removed
Site work grading
Rolling out compacted dirt
Site Access Plan
English
Site Access Plan
Spanish
Progress Photos
Aerial of demolition of auditorium space. Areas of work to happen within the construction zone, are highlighted in yellow
Aerial of demolition work and SSIMS/SCES. Areas of work to happen within the construction zone, are highlighted in yellow
Sidewalk at SSIMS entry backfilled
Materials are being sorted for load-out. Metal to the left of the excavator and spoils/debris to the right.
Metal being hauled off site
Site Access Plan
English
Site Access Plan
Spanish
SSIMS Demolition
Final piece of the building demolition
February 2024